1 · Why this matters

Established The prize is a number that planners can build to: how many gigawatts of data-centre load will actually be drawing power in 2030, as distinct from how many have been requested. As of November 2026 the two differ by more than an order of magnitude. Texas had 445.8 GW of large-load applications on file in April 2026, 9.0 GW approved to energise, and 3.9 GW as the most those approved loads had ever drawn at once. One consultancy counted 1,066 GW requested across the United States and expected about 28% of it to be served.

Frontier The magnitude of getting it right is measured in capacity that is either built and idle or missing and expensive. United States data centres used about 176 TWh in 2023, 4.4% of national electricity. The national laboratory that produced that figure, LBNL, projects 649 TWh in 2030 in its reference case, inside compounded bounds of 521 to 843 TWh. The gap between those bounds, 322 TWh, is nearly twice everything the sector used in 2023. Utilities told regulators in 2025 to expect 166 GW of peak growth by 2030, of which about 90 GW was data centres; the analysts who compiled that figure think the data-centre share is overstated by roughly 25 GW.

Established Who gains from a better number is mostly not the party asking for the power. In PJM, the largest United States market, the independent monitor attributed $9.3 billion of one capacity auction and $6.3 billion of another to data-centre load, forecast and actual, and those costs are spread across 67 million people. A forecast that is too high buys plant and wires that ordinary customers pay down for decades; one that is too low produces the scarcity prices already observed. Canada meets the same question on a smaller base, about 1.4 GW of live capacity in September 2025 against roughly 19,565 MW of connection requests in Alberta alone by July 2026.

Handwave The condition is that somebody measures it, and as of November 2026 nobody is required to. No United States agency surveys data-centre electricity use; the last federal pilot contacted 50 facilities and heard from nine. Every national total in this brief is a model built from equipment shipments, and every forward figure rests on a filing whose author has reasons to round up. Section 5 sets out why the gap persists, and section 7 names the observation that would close it.

2 · Concept overview

Established This brief is about two quantities that are routinely confused: energy already consumed, in terawatt-hours, and capacity requested or announced, in gigawatts. A terawatt-hour is a billion kilowatt-hours and is what a meter records after the fact. A gigawatt is a rate, and when it appears in a press release or an interconnection filing it describes the largest draw a developer wants the right to make, not what will be drawn. A facility with 1 GW of contracted capacity running at a 60% load factor uses about 5.3 TWh in a year; the same facility never built uses none.

Established Between a request and a kilowatt-hour sit at least six stages, and a load can stall or vanish at each. An inquiry becomes an application; an application may or may not have engineering studies submitted; studies lead to a signed service agreement with financial security; the agreement leads to construction of the substation and the building; the grid operator then grants approval to energise; and only after that does the meter show a draw, which ramps over months or years as servers are installed. Published queue totals usually count the first or second stage. Published consumption counts the last.

Established Three layers of overhead separate a chip from the grid. Information-technology load is what the servers draw. Facility load adds cooling and power conversion, and the ratio of the two is the power usage effectiveness, about 1.09 for the best large fleets and near 2 for a small server room. Grid load is what the utility must plan for, which depends on whether the facility draws from the network, generates on site behind its own meter, or sits beside a power station and takes its output directly, an arrangement called co-location.

Frontier The category boundary moves the answer. Most national estimates exclude cryptocurrency mining, which shares the queues and the tariffs but not the workload. Some count only purpose-built facilities; others include server closets in office buildings. Estimates of the share attributable to artificial intelligence depend on classifying servers by the accelerator chips inside them, which the operators know and seldom publish.

Established What this brief does and does not own. The supply chain between a model and a megawatt — packaging, transformers, turbines, permits — belongs to The Physical Stack of AI. The thermodynamic and device limits on energy per operation belong to Ultra Efficient Computing Energy Systems. Who controls the resulting capacity belongs to Compute Concentration, and how a grid behaves when large electronic loads swing belongs to Grids Without Inertia. This brief owns the accounting: what has been measured, what has been forecast and how those forecasts have fared, what is in the queue against what is energised, and who pays.

3 · Current scientific position

Established The measured record for the United States is a flat decade followed by a steep four years. The Lawrence Berkeley National Laboratory (LBNL) series puts data-centre consumption near 60 TWh from 2014 to 2016, 76 TWh in 2018 (1.9% of national electricity) and 176 TWh in 2023 (4.4%), cryptocurrency excluded. For 2024 the International Energy Agency (IEA) gives about 180 TWh and the Electric Power Research Institute (EPRI), which is funded by utilities, gives 177 to 192 TWh, about 5% of the national total.

Established The world total is smaller relative to the system and growing at a similar pace. The IEA series gives about 415 TWh in 2024, roughly 1.5% of world electricity, and 485 TWh in 2025. Growth in 2025 was 17%, and consumption by facilities built around accelerator chips grew 50%. The IEA projects about 950 TWh in 2030, around 3% of world demand.

Established None of those figures is a meter reading. They are bottom-up models: shipments of servers, storage and network equipment, multiplied by measured power per device and an assumed utilisation, plus simulated cooling. No United States agency collects the consumption directly. A 2021 pilot survey by the Energy Information Administration (EIA) approached 50 facilities and received nine responses. The IEA counts open electricity-data policies as covering 10% of world consumption.

Established Billing data provide the one independent check, and it agrees in direction. Commercial electricity sales in Virginia rose by nearly 30 million MWh between 2019 and 2025, faster than in any state except Texas, and the EIA attributes the rise largely to data centres. Summer peak in the utility zone covering most of the state reached 23,905 MW in 2025, 23% above 2019; the 2025–26 winter peak of 25,413 MW was 45% above the winter of 2019–20. A state audit body counted about 150 facilities and roughly 5,050 MW of load in northern Virginia in December 2024, and EPRI puts data centres above 20% of the state’s electricity.

Established The first documented forecasting failure ran high, not low. Through the 2010s computing output rose several-fold while data-centre electricity stayed roughly flat, about 194 TWh worldwide in 2010, because virtualisation, hyperscale consolidation and better cooling absorbed the growth. Analyses that extrapolated demand without modelling efficiency had predicted rapid increases that did not arrive. A 2022 review examined 258 estimates from 46 publications issued between 2007 and 2021 and judged that only two sources produced reliable figures.

Established The second failure ran low, between 2022 and 2025. Aggregated United States utility forecasts of five-year peak growth stood at 24 GW in the 2022 filings, 38 GW in 2023, 64 GW in 2024 and 166 GW in 2025, a sixfold revision in three years. About 90 GW of the 2025 figure, 55%, is data-centre load. The 2022 forecast by PJM, the operator serving 67 million people from Illinois to Virginia, for its Virginia zone showed 5,700 MW of growth by 2037; by August 2025 the same operator showed more than 20,000 MW of data-centre growth over that period.

Frontier The same sources that revised up have begun to revise down. Grid Strategies, the consultancy that compiled the 166 GW figure, judges its data-centre component overstated by roughly 25 GW, about 40% above what market analysts expect, and found some filings assuming a 96% load factor for new loads. PJM’s January 2026 forecast cut its summer peak by 2,564 MW for 2026, 4,414 MW for 2028 and 1,630 MW for 2031 relative to the forecast issued a year earlier, citing improved vetting of requested large-load adjustments, while raising its ten-year growth rate from 3.1% to 3.6% a year. Expected growth in its Virginia zone fell from 6.3% to 5.4% a year.

Frontier The national projections disagree by a factor of two, and the disagreement has widened. LBNL’s December 2024 report gave 325 to 580 TWh by 2028, or 6.7% to 12.0% of national electricity. Its June 2026 update gives 649 TWh in 2030, 11.8%, with single-factor sensitivities from 578 to 782 TWh and compounded bounds of 521 to 843 TWh. EPRI gives 383 to 793 TWh in 2030, or 9% to 17%. The IEA’s base case implies about 420 TWh. The low end of that set, 383 TWh, is 2.2 times the 2023 measurement; the high end is 4.8 times.

Established One forecast has a clean one-year check. The IEA reported in 2026 that the 17% growth observed in 2025 was in line with its projection of April 2025, and left its 2030 central case close to unchanged. This brief found no other projection issued since 2024 checked against an outcome by its own author.

Established The anchor result is the Texas queue set against the Texas meter. The April 2026 report of ERCOT, the Texas grid operator, listed 445.8 GW of large-load connection applications through 2033, up from 63 GW at the end of 2024, 226 GW in November 2025 and 233 GW in March 2026. Applications covering 321 GW had no studies submitted. As of March 2026, 9,042 MW had received approval to energise, and the largest simultaneous draw the operator had observed from those loads was 3,883 MW. The state’s record system peak is about 85.5 GW. By August 2026 the governor put requests near 474 GW, about 90% from data centres.

Established Other markets show the same shape wherever both numbers are published. In one Ohio utility territory whose peak has never exceeded about 10.5 GW, requests passed 30 GW, fell to about 13 GW after a tariff required payment for 85% of contracted demand, and stood at roughly 5.7 GW of signed contracts. In Malaysia, 38 projects held contracts for 5.9 GW of maximum demand in December 2024 and were drawing 405 MW.

Frontier Analysts’ estimates of how much of the queue is real range from one in seven to one in two. Wood Mackenzie counted 1,066 GW requested nationally, with about 12% holding firm service commitments and a further 17% judged likely, leaving some 768 GW it calls phantom load. Rapidan Energy puts the build-out at 20% to 30% of requests. Rystad Energy judges about half of applications credible in PJM and 14% in Texas. ERCOT itself expected roughly 100 GW of about 450 GW to survive screening.

Established What exists is a fraction of what is announced, and it is still large. A law-firm survey citing market data put live United States capacity at 40.6 GW in early 2026. A brokerage reported supply in the primary North American markets up 36% to 9,432 MW during 2025, with vacancy at 1.4%. Scarcity of finished, powered space is as well documented as the excess of requests.

Established On-site generation is real at a handful of sites and mostly gas. xAI’s Memphis site had 35 turbines capable of 422 MW on site in spring 2025, against 15 permitted,, and was permitted in July 2025 after more than a year of operation. Its second campus in Mississippi was permitted for 41 turbines and 1.2 GW on 10 March 2026, with about 20 already running. The Stargate campus at Abilene, Texas, was reported in January 2026 with 29 turbines of 34 MW each, 986 MW. The IEA expects 15 to 27 GW of on-site gas at data centres worldwide by 2030 and counts about one-fifth of United States projects as having begun land clearing or construction. A commercial tracker lists 59 behind-the-meter projects with about 90 GW of planned self-generation, a figure that describes plans.

Established The nuclear agreements have delivered no new megawatt-hour as of November 2026. The furthest advanced, the 835 MW restart of a Pennsylvania reactor under a 20-year contract signed in September 2024, is targeted for the second half of 2027, a year ahead of its original 2028 date. The largest contract for an operating plant, up to 1,920 MW over 17 years, was restructured in June 2025 from a behind-the-meter arrangement to ordinary grid delivery after the federal regulator rejected the expanded co-location in November 2024.

Established Capacity prices in PJM rose elevenfold in two auctions and have stayed at an administrative cap. Clearing prices were $28.92 per MW-day for 2024/25, $269.92 for 2025/26, $329.17 for 2026/27, $333.44 for 2027/28 and $325 for 2028/29, the last announced on 14 July 2026 with a reserve margin of 14.7% against a 20% target. The independent market monitor attributed 63% of the 2025/26 increase, $9.3 billion, to data centres, and $6.3 billion of the 2028/29 cost to data centres planned to be operating in that year.

Frontier The retail evidence through 2024 points the other way. LBNL and the Brattle Group found that states with the fastest load growth from 2019 to 2024 saw real average prices fall, with load growth lowering prices by roughly 0.6 cents per kWh on average. An EPRI causal study of 2015 to 2024 found residential prices about 3.5% lower per doubling of data-centre capacity. Both sets of authors say the relationship may not hold once new supply is constrained, and the laboratory found the effect loses statistical significance for residential prices alone.

Established Energy per unit of work is falling fast where anyone has measured it. Google reported 0.24 Wh for its median Gemini text prompt in May 2025, including idle machines, host processors and facility overhead, down 33-fold in twelve months; the narrower chip-only figure was 0.10 Wh. The figures exclude model training and were not independently verified. The IEA describes energy per task as falling by at least an order of magnitude a year, and reasoning and agentic tasks as taking hundreds to thousands of times more energy than simple text generation.

Established Most of the water is used at the power station, not the data centre. LBNL estimated 17.4 billion US gallons, about 66 billion litres, consumed on site by United States data centres in 2023, and 211 billion gallons, about 800 billion litres, consumed in generating their electricity, twelve times as much. Meta’s 2024 disclosure shows 2,974 megalitres at its sites and 72,207 megalitres embedded in purchased electricity.

Established Canada has little measured data and four different rationing rules. Live capacity was about 1.4 GW in September 2025. Alberta’s operator capped new large-load connections at 1,200 MW in June 2025 against more than 16 GW of requests and a peak then near 12 GW; the allocation went to two projects of 970 MW and 230 MW, and by 30 July 2026 the connection list held about 19,565 MW against a record peak near 12,800 MW. British Columbia will release 300 MW for AI facilities and 100 MW for conventional ones between February 2026 and February 2028. Québec requires ministerial authorisation above 5 MW. Ontario’s planner expects data centres to reach 8.6% of provincial demand in 2050, about 60% more than it previously forecast.

4 · Frontier questions

Frontier How much of the queue converts, and on what schedule, is the open question on which everything else turns. The published estimates run from 14% to about 50% depending on market and analyst, and none rests on an observed cohort followed from application to draw. ERCOT’s own expectation that about 100 GW of roughly 450 GW would survive screening is an expectation. The audit ordered by the Texas governor on 3 August 2026, covering every data centre seeking access to the main grid, is the first attempt to examine a whole queue; no result from it had been published as of 13 November 2026.

Frontier What load factor a large AI campus runs at is unmeasured in public. Some utility filings assume 96%. A facility that trains models in bursts and serves inference on a daily cycle would run lower, and each ten points of load factor on 90 GW is about 79 TWh a year. The ratio between ERCOT’s 9.0 GW approved and 3.9 GW observed peak is 43%, but it mixes ramp-up, partial build-out and genuine under-use, and cannot be read as a load factor.

Frontier Whether efficiency outruns demand is the oldest dispute in the subject and it has not been settled by the 2020s. Per-task energy is falling by an order of magnitude a year on the IEA’s reading, and one operator reports a 33-fold fall in twelve months. Over the same period consumption by AI-focused facilities grew 50% in a year. The 2010s resolved this in favour of efficiency; 2023 to 2025 resolved it in favour of demand. Which regime 2027 to 2030 belongs to depends on how elastic demand for inference is to its price, which nobody has published.

Speculative Reasoning and agentic workloads could dominate the total, and the multiplier is a range of three orders of magnitude. The IEA puts such tasks at hundreds to thousands of times the energy of a simple text reply, and estimates that answering every web search with a simple AI text reply would take under 4 TWh a year, less than 1% of 2025 consumption. The first figure makes the second irrelevant if usage shifts, and no operator publishes the mix.

Frontier Whether historical load growth lowering retail prices survives a supply-constrained decade is contested between people reading the same data. LBNL and Brattle show the 2019 to 2024 relationship and call its extension unclear. The PJM market monitor shows $23 billion of added capacity cost over three auctions and attributes most of it to data-centre load. Both can be true: the first describes average retail prices in states with spare capacity, the second describes a wholesale market without it. The unresolved part is which condition will describe most of North America by 2030.

Frontier Whether on-site generation removes a load from the grid or only from the queue is disputed in law and in engineering. The federal regulator’s position since November 2024 is that proximity to a power plant does not take a data centre off the transmission system, and its December 2025 order required PJM to create three new transmission services for co-located load. Developers who build off-grid entirely avoid that question and acquire another: the IEA finds on-site gas must be overbuilt by 30% to 70% relative to demand to match grid reliability.

Speculative The size of the installed base that could be stranded is unknown in both directions. If accelerator chips are retired after three years, not six, LBNL’s 2030 figure falls from 649 to 590 TWh; if idle power and utilisation run higher it rises to 782 TWh. Those sensitivities describe hardware behaviour that the owners observe daily and that no outside party can check.

Frontier Whether flexibility is real at scale has moved from proposal to rule without a public demonstration. British Columbia requires applicants to show willingness and ability to curtail on 24 hours’ notice; PJM planned a data-centre curtailment mechanism by the end of 2026; some states price firm and interruptible service separately. The IEA records server load swinging by more than half of rated capacity within a second, which is flexibility of a kind grid operators do not want. Published evidence of a gigawatt-scale campus curtailing on instruction is something this brief could not find.

5 · Technological bottlenecks

Established The first bottleneck is that the quantity is not measured. National totals come from a model maintained by one laboratory and cross-checked by one agency and one industry institute, all drawing on overlapping shipment data. The EIA’s attempt at a survey drew nine responses from 50 facilities, and its 2024 survey of cryptocurrency mining was halted by a court order and its data destroyed by agreement. PJM’s own May 2026 accuracy report notes that it lacked hourly historical data for data centres to separate from its 2024 load history.

Established The second is that requesting capacity has been nearly free. A developer could file for the same campus with several utilities and hold a place in each queue. Where a price was attached, requests fell: by more than half in one Ohio territory once payment for 85% of contracted demand was required. Texas legislation requires a $100,000 interconnection fee and disclosure of duplicate requests; as of late May 2026 more than 300 GW of its queue still had no studies submitted.

Frontier The third is that the forecaster is rarely disinterested. A utility earns a regulated return on plant built to serve forecast load. A developer’s site is worth more with a queue position. A grid operator is blamed for shortage, not for surplus. The independent consultancy that aggregates the filings, the market monitor and the consumer advocates each have their own clients. This brief found no forecaster whose incentives are symmetric about the error.

Established The fourth is physical: wires and machines arrive more slowly than buildings. Gas-turbine and step-up-transformer lead times have each lengthened to three or four years from about eighteen months, and for heavy-frame gas turbines further: in October 2026 the largest maker was taking reservations for delivery in 2032 (see The Physical Stack of AI). PJM’s analysis found that existing transmission could not carry the full 835 MW of the restarted Pennsylvania reactor until lines expected in December 2030 are built, which is why its owner sought to transfer 760 MW of interconnection rights from another plant. PJM’s queue held about 54 GW of generation with agreements and about 48 GW under construction in January 2026, against retirements it forecasts at 40 GW between 2022 and 2030.

Established The fifth is that the market for capacity has stopped clearing. PJM’s last two auctions cleared at or near a cap approved by the federal regulator and short of the reliability requirement, by 6,623 MW for 2027/28 and 6,831 MW for 2028/29. A price that cannot rise does not ration, and the operator’s response has been administrative: a backstop procurement of 15-year contracts for new generation targeted for September 2026, and an expedited interconnection track for ten projects a year. This brief could not confirm whether the backstop auction was held on schedule.

Frontier The sixth is that tariffs meant to protect other customers are untested against a default. Minimum-take terms of 60% to 90% over 10 to 30 years bind only as long as the counterparty exists. Wood Mackenzie observes that first-time developers hold disproportionately large requests and are less likely to build. A tariff’s collateral, $1.5 million per MW in one Virginia case, is the measure of how much of that risk has actually been moved.

Handwave The seventh is that the demand itself rests on revenue that has not yet been earned. Hyperscale capital expenditure passed $400 billion in 2025 and was expected to rise another 75% in 2026. Whether the services sold from that plant will pay for it is outside this brief, but every gigawatt forecast above assumes they will, and no electricity forecast this brief read states that assumption or tests it.

6 · Research dependencies

Established The subject depends first on equipment-shipment and power-draw data that only a few firms hold. The LBNL model is built from planned shipments of servers and accelerators and per-device energy; its 2026 sensitivities show the result moving by more than 100 TWh on assumptions about chip lifetime and idle power. Independent measurement of fleet utilisation would narrow the range more than any amount of further modelling.

Established It depends on device and system efficiency continuing to improve, which is the subject of Ultra Efficient Computing Energy Systems, and on the delivery chain for transformers, turbines and switchgear described in The Physical Stack of AI. Rack power density rose elevenfold between 2020 and 2025 on the IEA’s figures, with a further fourfold rise expected by 2027; cooling and power distribution inside the building were being designed around that by 2025.

Frontier It depends on firm supply that can be added in the same decade. Gas is the only source being added behind the meter at gigawatt scale as of November 2026. The restart and uprate of existing reactors is the nearest nuclear contribution; new designs are treated in Small Modular Reactors and Advanced Fission, and the earliest dates attached to data-centre agreements for them fall in the 2030s. Batteries enter as a buffer: the IEA expects 20 to 25 GW installed at data centres by 2030, and storage is covered in Energy Storage Revolutions.

Frontier It depends on grid-code and protection work for large electronic loads. North American reliability standards for large loads were expected in the second quarter of 2026, according to a law-firm account of the Alberta operator’s June 2025 briefing; this brief could not confirm their publication. The behaviour of inverter-rich systems under sudden load loss is the subject of Grids Without Inertia.

Speculative And it depends on a question no energy agency can answer: how much computation people and firms will buy at the prices of 2028. The technology-forecasting record on questions of this kind is examined in Technology Forecasting.

7 · Required experiments

Frontier The decisive observation is a conversion ratio, and one grid already publishes both of its terms. The decisive observation is how much of ERCOT’s large-load queue is approved to energise, and how much of that is observed drawing power, at the end of 2028 compared with the 9,042 MW approved and 3,883 MW observed in spring 2026. If observed draw passes 20 GW by then, the high forecasts are roughly right and the queue was a leading indicator. If it stays under 10 GW, the queue was mostly options, and the national projections built on utility filings fall with it.

Frontier The Texas audit is the first natural experiment on a whole queue. Ordered on 3 August 2026 and applying to every data centre seeking access to the main grid, it will show how many applicants can document land, financing and customers. Its design matters as much as its result: an audit that removes duplicates but accepts self-declared demand will measure paperwork. No finding had been published as of 13 November 2026.

Established The tariff experiment has already run once and should be repeated in public. When one Ohio utility attached an 85% minimum payment to requests, its pipeline fell from about 30 GW to about 13 GW and signed contracts settled near 5.7 GW. Twenty-three states had approved large-load tariffs by May 2026 and seven more were pending. Each is a trial of the same intervention with different terms, and a table of requests before and after, by tariff term, would say what a firm commitment costs to elicit. Nobody has compiled it.

Frontier A forecast audit is cheap and has not been done. Every utility that filed a five-year load forecast in 2022 has four years of outcomes against it. Comparing filed large-load additions with metered additions, utility by utility, would show whether the upward revisions of 2023 to 2025 were corrections or overshoots. PJM’s accuracy report began this for its own footprint in May 2026 and found it lacked the historical data to finish.

Frontier A mandatory survey would settle the base year. A federal collection of annual consumption, peak demand and on-site generation from every facility above a size threshold would replace the shipment-based model with meter data. The technical obstacle is small; the 2021 pilot failed on response rate, and the 2024 crypto-mining survey failed in court.

Frontier The retail-price question needs a design that separates constrained from unconstrained markets. The LBNL and EPRI studies cover 2015 to 2024, before the capacity auctions that cleared at the cap. Repeating them on 2025 to 2028 data, with states grouped by reserve margin, would show whether the sign of the effect flips where supply is short.

Speculative A published load shape from one gigawatt-scale AI campus would do more than any model. Hourly draw over a year, with the split between training and inference, would fix the load factor, the swing and the curtailable fraction at once. Operators hold this and have no obligation to release it; this brief found no instance of one doing so.

Frontier The efficiency claim needs a second measurer. Google’s per-prompt figure is the operator’s own, covers text only and excludes training. A per-token energy figure reported to a common boundary by several providers, with the mean and upper percentiles alongside the median, would turn an anecdote into a series.

8 · Engineering requirements

Established The engineering problem for a grid is to serve a load that may be 100 MW or 1,000 MW, may arrive in 2027 or never, and wants an answer in months. Transmission and substation work takes three to five years, so the planner must commit before the load is certain. The devices that manage this are contractual: staged capacity, ramp schedules, minimum-take, collateral and withdrawal penalties. Each moves risk from the general customer to the applicant and each lengthens the path to a signature.

Established Density has changed the building. With rack power up elevenfold in five years and the heat from one rack compared by the IEA to that of 30 gas boilers, air cooling is being displaced by liquid loops. Closed-loop liquid and dry cooling cut on-site water toward zero at some cost in electricity; one industry-aligned analysis puts the reduction from dry cooling above 90% for a fan load of 1% to 1.5% of output.

Frontier Self-supply is a power-station project attached to a data-centre project. A campus on reciprocating engines or aeroderivative turbines needs fuel supply, air permits, spare units and black-start. Early off-grid sites were reported in 2026 to have suffered turbine failures, including one event needing about a day of diesel backup. The IEA’s 30% to 70% overbuild is the engineering expression of what the grid otherwise provides.

Frontier Co-location beside an existing plant is quicker to energise and slower to approve. It uses a generator and switchyard that exist, but it removes that output from the pool serving other customers, and the regulator’s December 2025 order treats the load as a transmission customer with firm, non-firm or interim service. One industry analysis counts about 2,885 MW of reported co-location projects in ERCOT, including a 1,200 MW arrangement at a nuclear plant ramping to 2032.

Established Water engineering is sized to the hottest day. Evaporative systems use most of their water at peak temperature, so an annual average understates what the local utility must supply. The IEA’s illustration for a 100 MW facility is about 2 million litres a day in total, of which roughly 725,000 litres is consumed on site. In one Oregon city a single operator’s facilities took 355 million of 1.232 billion gallons of municipal supply, 29%.

Speculative Load-side flexibility is an engineering option whose value depends on numbers not yet published. If a campus can shed a known fraction for a known number of hours, it can connect ahead of new transmission and avoid setting the system peak. The fraction and the hours are properties of the workload. Rules that require curtailment capability, as in British Columbia, will produce the first data.

9 · Adjacent technologies

Established Cryptocurrency mining is the closest precedent and shares the queue. It is a large, location-flexible, interruptible electrical load that arrived quickly, was forecast badly and is excluded from most data-centre totals. Québec prices it separately, at 19.5 cents per kWh from the second half of 2026 subject to approval, and British Columbia’s rules allow its allocation to be capped. Its record of curtailing for payment in Texas is the nearest thing to evidence on large-load flexibility.

Established Gas turbines and reciprocating engines are the adjacent technology actually being bought. Turbine orders rose 70% in 2025 on the IEA’s count. The constraint is manufacturing slots, which is why secondary-market and aeroderivative units appear at data-centre sites.

Frontier Firm low-carbon supply is adjacent in ambition and distant in schedule. Reactor restarts, enhanced geothermal and long-duration storage are each named in data-centre procurement. Their measured state is set out in Small Modular Reactors, Geothermal Megaprojects and Energy Storage Revolutions; none supplies a gigawatt to a data centre as of November 2026.

Frontier Electrification of heat and transport is the other source of load growth and is forecast with the same instruments. The 166 GW utility aggregate includes about 30 GW from industry and manufacturing and about 30 GW from buildings and vehicles. In Ontario’s 2026 outlook electric vehicles, not data centres, account for more than half of the uncertain growth margin. Industrial Heat Electrification covers that side.

Speculative Efficiency at the chip is adjacent in mechanism and opposite in sign. One cloud vendor claims 30% to 40% better price-performance per generation of its own accelerators, and one model provider cut its introductory prices by 75% in April 2026. Cheaper inference lowers energy per task and, if demand is elastic, raises the total.

10 · Institutional requirements

Established In the United States the question is split between a federal regulator that governs transmission and wholesale markets, state commissions that set retail tariffs, and regional operators that forecast and plan. None of the three owns the load forecast end to end. Utilities submit large-load adjustments; operators vet them; commissions approve the plant that follows. PJM’s January 2026 rule that near-term loads must hold an electric service obligation or construction commitment to be counted, with later projects treated as non-firm and derated, is the first formal separation of firm from speculative load in a regional forecast.

Established The federal position on co-location was set in three steps. In November 2024 the regulator rejected an amended agreement that would have raised a co-located load at a Pennsylvania nuclear plant from 300 MW to 480 MW. On 18 December 2025 it found PJM’s tariff unjust and unreasonable for generators serving co-located load and ordered three new services, with a three-year transition for existing arrangements ending 18 December 2028. In June 2026 it issued show-cause orders on large-load tariffs. This brief could not confirm the status of a national large-load interconnection rule as of November 2026.

Established State tariffs are where cost allocation is actually being decided. Virginia’s commission approved a class for loads of 25 MW and above in November 2025, effective January 2027, with 14-year contracts and payment for 85% of contracted transmission demand and 60% of generation demand regardless of use. Oregon approved 90% minimum demand charges and 10- to 30-year terms on 7 May 2026 and estimated data-centre rates up 29% and residential rates down 1.3% as a result. Michigan requires 15-year terms and 80% minimum billing. Pennsylvania adopted a model tariff on 30 April 2026. One count finds 77 large-load tariffs pending or in place across 36 states.

Frontier The consumer advocates’ case is that the wholesale market passes the cost through before any state tariff can act. Wholesale costs make up roughly 55% to 70% of bills in PJM states, and the advocates’ May 2026 statement describes load growth apart from data centres as flat to negative over ten years. On that reading the capacity charge is a transfer from existing customers to new ones, and the remedy is to make large loads bring or buy their own capacity. PJM’s backstop procurement and its extended price collar for the 2028/29 and 2029/30 auctions are partial responses.

Frontier The industry’s case is that data centres pay full tariff rates on a large volume and that the capacity market is short for reasons that predate them. Retirements, slow interconnection and permitting delays appear in PJM’s own account: of delayed project milestones from 2023 to January 2026, 29% were attributed to permitting and 23% to supply chains. The two cases disagree less on facts than on which baseline counts as normal.

Established Texas has moved from open access to audit. After its queue grew sevenfold in sixteen months, the state adopted a fee and disclosure requirement, its operator told its board that it could no longer evaluate applications individually, and on 3 August 2026 the governor ordered an audit that in effect paused approvals. One research firm estimated that the order could delay almost a fifth of the United States pipeline in the medium term.

Established Canadian provinces have chosen rationing over queueing. Alberta fixed 1,200 MW through 2028 and split it between two projects after others withdrew; legislation in 2025 gave the minister and the operator powers over data-centre connections; and a 2% levy on computing hardware applies from 31 December 2026 to grid-connected facilities of 75 MW or more, falling to 1% for those that generate their own power and to nothing for those off the grid. The province’s own guidance describes a Data Centre Regulation in force since June 2026 that puts projects with dedicated generation at the front of the line, while a law-firm summary dated 14 July 2026 says no connection framework had been announced; this brief could not reconcile the two.

Established British Columbia and Québec ration by statute and price. British Columbia’s 2025 amendments and its February 2026 regulation cap AI facilities at 300 MW and conventional data centres at 100 MW over two years, limit any request to 145 MW, require $25,000 per MW in bid security, and halve the caps for the following year. Québec’s 2025 law requires the minister to authorise any new load of 5 MW or more; its utility expects data-centre demand to grow sevenfold to more than 1,000 MW by 2035 and asked in February 2026 for a rate about double the large-power tariff. Whether the regulator approved that rate is something this brief could not confirm. Ontario introduced legislation in June 2025 to prioritise connections by economic and strategic benefit; this brief did not confirm its passage.

Handwave No jurisdiction this brief examined requires the applicant to publish what it later uses. Tariffs secure payment and forecasts are vetted, but the realised draw of an approved load is commercial information almost everywhere. An institution that closed that loop would cost little and would be the first of its kind.

11 · Ethical & societal considerations

Established The distributional question is who carries the cost of a forecast that turns out wrong. If load arrives, new plant is used and paid for by those who use it. If it does not, the plant sits in the rate base of customers who never asked for it. Minimum-take tariffs move part of that risk; capacity markets, which price the forecast itself, do not.

Frontier Whether data centres are subsidised by other ratepayers or subsidise them is a dispute about allocation method, and both sides cite real numbers. The market monitor’s $6.3 billion and $9.3 billion are counterfactual estimates of what the auction would have cost without the data-centre load. The LBNL and EPRI findings are observed price changes. One advocacy estimate puts the increase facing the average PJM household near $70 a month by 2028; one consultancy projected residential rates 30% to 60% higher by 2030. These are projections by interested or commissioned parties and are reported here as claims.

Established Local burdens fall on identifiable places. On-site turbines ran for more than a year at one Tennessee site before an air permit was issued, in a district whose residents and their advocates had objected; the same developer’s Mississippi site was permitted over objections that the draft understated pollution. Water for evaporative cooling is drawn from municipal systems that were sized for towns. The benefit of the computation is distributed globally.

Frontier Secrecy has a cost that is borne by planners and the public. Utilities sign non-disclosure agreements with applicants, so the identity and firmness of the largest loads in a forecast are often unknown to the commission approving the plant. The EIA’s failed surveys and the absence of site-level water and energy disclosure are the same problem at national scale. Disclosure thresholds near 1 MW have been proposed even by analysts sympathetic to the industry.

Frontier The climate accounting is unsettled and should not be asserted either way. The IEA projects data-centre emissions near 350 million tonnes in 2035, about 2% of power-sector emissions, and separately estimates that AI applications could save more than 13 EJ of energy by 2035. The first is a projection of a measured trend; the second is a potential. Operators report market-based emissions that net out purchased clean energy; location-based figures, which describe the grid actually drawn on, are published less often.

Speculative Intergenerational fairness enters through asset life. A gas plant or a transmission line built for a 2028 load is paid for through the 2050s. If the workload moves, shrinks or becomes ten times more efficient, the asset remains. The opposite error, building too little, shows up sooner and is easier to see, which is one reason institutions lean toward building.

Handwave Whether the computation is worth the electricity is a values question this brief does not answer. Polling cited by the utility industry’s own research institute finds about 70% of Americans opposed to a data centre near them. That is evidence about siting, not about the value of what the sites produce, and treating either as settling the other is an error in both directions.

12 · Civilizational implications

Frontier After roughly two decades of flat load, several North American grids are planning for sustained demand growth, and the largest single cause is one industry. PJM’s record peak was set in 2006; its ten-year forecast is 3.6% a year in peak and 5.3% in energy. The IEA attributes nearly half of United States demand growth to 2030 to data centres. Institutions built to manage flat load are relearning how to forecast, site and finance, and are doing so on the word of applicants.

Speculative If the high forecasts are right, electricity policy becomes industrial policy for computation. At 843 TWh, data centres would take about 15% of United States electricity in 2030, and where they locate would follow where power can be had. Alberta’s levy and bring-your-own-power priority, and British Columbia’s caps, are early forms of jurisdictions choosing how much of this they want.

Speculative If the low forecasts are right, the 2020s will be remembered for a queue. A sector at 383 to 521 TWh in 2030 is a large industrial load that grids absorbed in the past. The lasting effects would then be the gas plant, the tariffs and the capacity charges procured against the higher number.

Frontier Either way, the episode is a test of whether public institutions can obtain information from private firms in time to plan. The published estimates for 2024 agree to within about 8%. The forward record is a set of filings. The difference is institutional, and it will recur with the next large, fast, privately planned load.

Handwave Claims that AI demand will consume a majority of national electricity, or that efficiency will make the question disappear, are both in circulation and neither has a model behind it that survives its own sensitivity analysis. The widest published bounds for 2030 are 9.5% to 15.3% of United States electricity.

13 · Timelines

These horizons separate what is dated by a meter or a regulator’s order from what is dated by a developer or a forecaster. Dates already passed are given with what was expected beforehand.

  • Already happened: Established The flat decade and the break. United States consumption held near 60 TWh from 2014 to 2016, reached 76 TWh in 2018 and 176 TWh in 2023. PJM capacity prices rose from $28.92 to $269.92 per MW-day between the 2024/25 and 2025/26 auctions. The federal regulator rejected expanded co-location in November 2024 and ordered new rules on 18 December 2025. ERCOT’s queue went from 63 GW at the end of 2024 to 445.8 GW in April 2026.
  • 2026 to 2028: Frontier The dates that will test the announcements. The Pennsylvania reactor restart was first scheduled for 2028 and, as of July 2026, was targeted for the second half of 2027. Virginia’s large-load tariff takes effect in January 2027. Alberta’s 1,200 MW allocation covers connections through 2028, and its hardware levy begins on 31 December 2026. British Columbia’s first allocation window closes on 1 February 2028. PJM’s 2028/29 delivery year, already procured 6,831 MW short, begins on 1 June 2028. LBNL’s 2024 report expected 325 to 580 TWh in 2028; the next edition will be the first to face that range with data.
  • 2030: Frontier The year most forecasts name. LBNL’s reference case is 649 TWh for the United States; EPRI’s range is 383 to 793 TWh; the IEA’s world figure is about 950 TWh. Utilities’ filings imply about 90 GW of new data-centre peak, analysts about 65 GW. The IEA expects 15 to 27 GW of on-site gas. Transmission needed to carry the restarted reactor’s full output is expected in December 2030.
  • 10 yr: Speculative To 2036. PJM forecasts a summer peak of 222,106 MW against a record of 166,929 MW set in 2006. Agreements for new reactor designs carry dates from 2030 to 2035, which this brief treats as developers’ schedules. Québec expects more than 1,000 MW of data-centre demand by 2035. Whether per-task efficiency gains of an order of magnitude a year persist for a decade is unknown; they did not need to in the 2010s for consumption to stay flat.
  • 25 yr: Speculative To about 2050. Ontario’s planner puts data centres at 8.6% of provincial demand in 2050 within total growth of 65% to 250 TWh. PJM’s twenty-year forecast reaches 253,077 MW in 2046. Forecasts at this range have no track record for this load; the five-year ones were revised sixfold in three years.
  • 50 / 100+ yr: Handwave Beyond mid-century. Any figure for data-centre electricity past 2050 is an extrapolation of a trend that has changed sign twice in fifteen years. The physical ceiling on computation per joule is treated in Ultra Efficient Computing Energy Systems; the economic ceiling on how much computation is wanted has no theory at all.

14 · Technology tree & dependencies

  • Depends on Device and system efficiency trends in Ultra Efficient Computing Energy Systems and the equipment delivery chain in The Physical Stack of AI. Neither blocks the question this brief asks, which is one of measurement and allocation; no scientific result on this map has to arrive first.
  • Requires (not on this map) A requirement that facilities above a size threshold report annual consumption, peak and on-site generation, which no North American jurisdiction imposes as of November 2026. A rule separating firm from speculative load in every regional forecast, as PJM adopted in January 2026. Tariffs whose minimum-take and collateral terms have been tested against a counterparty that failed. Manufacturing capacity for turbines and step-up transformers, where lead times run three to four years. Routine publication, by every operator, of how much queued load has been approved and how much is drawing. And one published hourly load shape from a gigawatt-scale AI campus, which would fix the load factor every forecast assumes.
  • Enables A defensible planning number for generation, transmission and capacity procurement, and with it a basis for allocating cost. It also sets the scale of the firm-power market that reactor, geothermal and storage developers are selling into, and the size of the grid-stability problem large electronic loads pose.
  • Adjacent Compute Concentration, for who holds the capacity once it is energised; Grids Without Inertia, for system behaviour under large inverter-coupled loads; Small Modular Reactors and Geothermal Megaprojects, for the firm-supply claims attached to data-centre contracts; Water Infrastructure Megaprojects; and Technology Forecasting, for the general record of forecasts like these.

15 · Common misconceptions & speculative claims

Handwave “Data centres have requested a thousand gigawatts, so a thousand gigawatts are coming.” The 1,066 GW national count equals 83% of all United States utility-scale generation. The analysts who produced it expect 28% to be served. In Texas 2% of requested capacity had approval to energise and under 1% had been observed drawing. A queue measures the price of asking.

Handwave “The queue is all phantom, so there is no demand problem.” United States consumption nearly tripled between 2014 and 2023. Virginia’s commercial sales rose by 30 million MWh in six years and its winter peak by 45%. Vacancy in the main North American markets was 1.4% at the end of 2025. Capacity auctions have cleared short twice. The measured growth is enough to explain the scarcity without any of the unbuilt requests.

Established “Each AI query uses a bottle of water.” A widely repeated estimate put a 100-word reply near half a litre. The one operator that has published a measured figure reports 0.24 Wh and 0.26 mL for a median text prompt, on-site water only, training excluded. The older figures were estimates made without access to production data; the newer one is unaudited and covers the cheapest kind of task. The honest range for a reasoning task is hundreds to thousands of times the simple one, on the IEA’s account.

Frontier “Efficiency gains mean total demand will fall.” They did hold demand flat from 2010 to 2018. From 2024 to 2025 per-task energy fell by an order of magnitude and AI-focused consumption rose 50%. An efficiency gain lowers the total only if demand grows more slowly than efficiency improves, and that is an empirical matter that has gone both ways.

Frontier “Data centres are raising everyone’s bills.” Through 2024, states with fast load growth saw real prices fall, and no study this brief read finds load growth among the causes of the 2019 to 2024 increases. From 2025 the PJM capacity market tells a different story for 67 million people. The statement is false as history, true of one wholesale market, and unproven as a national forecast.

Frontier “Data centres lower everyone’s bills by spreading fixed costs.” That mechanism is real where the network has spare room. It reverses where new load forces new plant at prices above the existing average, and the authors of the studies most often cited for it say so. The residential effect, as distinct from the all-customer average, was not statistically significant in the national laboratory’s work.

Speculative “Behind-the-meter power means no burden on the grid.” A campus that never connects imposes no transmission cost. Most on-site projects also seek a grid connection for backup or eventual supply, the federal regulator treats co-located load as a transmission customer, and the gas a campus burns is drawn from the same pipelines as utility generation. About 90 GW of planned self-generation is tracked; how much will be islanded for its whole life is not reported.

Handwave “Nuclear power is running AI.” As of November 2026 the agreements have added no reactor output. The one restart under construction is expected in the second half of 2027. Contracts with operating plants reassign electricity that was already on the grid. One tracker lists about 9.8 GW of contracted or announced reactor capacity for data centres, with new-design dates in the 2030s and no restart or new-build entry generating.

Established “Data centres drain local water supplies.” Direct consumption in the United States was about 66 billion litres in 2023, under 1% of national consumptive use on one industry-aligned reading of federal data, and it can be engineered close to zero. It is also concentrated: 29% of one Oregon city’s supply, about 2 billion gallons in northern Virginia in 2023, up 63% from 2019. The national figure and the local one are both correct and answer different questions. The larger volume, twelve times the direct figure, is evaporated at power stations and depends on how the electricity is made.

Handwave “The forecasts are converging.” LBNL’s range for the end of the decade moved from 6.7%–12.0% of national electricity in its 2024 report to 9.5%–15.3% in 2026. Utility five-year forecasts multiplied sixfold and were then trimmed. The spread across credible 2030 estimates is 383 to 843 TWh. The record to November 2026 is of forecasts chasing the latest data in whichever direction it last moved.

Speculative “Canada’s cold climate and hydro make it the natural home for this load.” The hydro provinces are the ones rationing: 400 MW over two years in British Columbia, ministerial approval above 5 MW in Québec. The province with the largest queue, Alberta, is largely gas-fired and has capped grid connections at 1,200 MW while favouring projects that bring generation. Canada’s 1.4 GW of live capacity in 2025 was about 3% of the United States figure, and the constraint has been deliverable power, not climate.