Where it stands

Fervo Energy’s disclosures are most of the public record on enhanced geothermal power at commercial scale. Its first 33 MW unit at Cape Station in Utah entered commercial operation on 30 September 2026, on the schedule the company set in 2023, and the federal land agency has approved its environmental case for up to 2 GW there; that approval is the one claim on this page an outside body has checked. Everything else rests on the company’s own figures. They are specific, consistent over years, and include the unflattering ones: its Nevada demonstration averaged 2.1 MW gross and 1.4 MW net over 614 days against the 3.5 MW it announced, and its first 100 MW is expected to cost about $7,000 per kilowatt. No output, flow or temperature from Cape has been published. This page quotes no outside critic of these claims; the counter-case to each is the Institute’s reading of the company’s own figures. It holds 1,054 MW of binding contracts against one unit in commercial operation, and its business case lies in whether the drilling gains it reports bring the next 396 MW in at its $5,500 target by the end of 2028.

The company

Founded 2017; formed as a Delaware corporation on 27 May 2017 [2]
Headquarters Houston, United States [1]
Set up to make Electricity from enhanced geothermal systems: hot rock without natural permeability, opened with horizontal wells and multistage hydraulic stimulation adapted from shale oil and gas [2, 14]
Leadership Tim Latimer, chief executive and co-founder; Jack Norbeck, chief technology officer and co-founder; David Ulrey, chief financial officer; Sarah Jewett, chief operating officer [9]
Listing Nasdaq, as FRVO, since an initial public offering completed on 14 May 2026 with gross proceeds of about US$2.2 billion. Cape Phase I has a US$421 million non-recourse project debt facility, closed in March 2026, of which about US$287.5 million was drawn at 30 September 2026. [2, 5, 22]
Customers 1,054 MW under binding power-purchase agreements at 30 September 2026. At Cape: Southern California Edison (two 15-year agreements, 320 MW, 2024), Shell Energy, California community choice aggregators, and Google (396 MW for 15 years, 2026). Separately, in Nevada: an agreement of 2024 to supply 115 MW to Google’s data centres through NV Energy by 2030, whose binding status the sources read do not state. A 3 GW framework agreement with Google is not binding. [1, 2, 21, 22, 6, 25, 5]
Stated plans GeoBlocks 2 and 3 in commercial operation by 1 January 2027, completing about 100 MW; GeoBlocks 4 to 11, the 396 MW for Google, with first power in mid-2028 and full capacity by the end of 2028; a long-term development target of 1.1 GW by 2030; enhanced-geothermal wells in Idaho and an appraisal campaign in Nevada under two Energy Department awards totalling about US$20 million [1, 5, 11]

What it claims, and how far each claim has got

Each claim is placed on the Institute’s evidence ladder, which measures how far the public evidence for a claim has got, not whether the claim is true: Claimed, Described, Shown, Verified, Repeated and In use. The definitions are on the Frontier Companies page. Flags inside each assessment follow the rest of the site: Established, Frontier, Speculative and Handwave.

A 30-day test at Project Red, Nevada, reached “a flowrate of 63 liters/second”, and the well pair “can support 3.5 MW of electricity production”

Said 18 July 2023 · Shown

Established The test happened, and the plant has supplied the Nevada grid since November 2023. Established The company’s own operating record does not bear out the announcement as a running rate: 2.1 MW gross is 60% of 3.5 MW, and net output, after the plant’s own use of power, is 40%. Converting units, 63 L/s of water at 175 °C is about 56 kg/s, so the 36 kg/s circulated is about two-thirds of the tested rate. Frontier The company’s case is that “the wells were not designed to be production-optimized”, that the outages were surface and grid faults rather than the reservoir, and that production temperature held for more than 500 days before a decline of about 1.4 °C that its models predicted. Its securities filing now calls Project Red “a limited-scope, proof-of-concept initiative”. Both readings come from the same numbers, which the company published itself, and 614 days is about one-eighteenth of a thirty-year plant life.

What is publicAn unreviewed company preprint on the test, and the company’s own account of 614 operating days, published in April 2026: about 2.1 MW gross and 1.4 MW net on average, roughly 36 kg/s circulating at about 175 °C, and 98.4% uptime outside several extended outages.
What is missingA production history by day or month, a metered record kept by anyone outside the company, and an account of why output and flow ran below the 2023 figures.
What would settle itA published production history, or plant-level generation in a government series, set against the 3.5 MW and 63 L/s.

Sources: 12, 14, 15, 16, 17, 2

A 30-day test at Cape Station, Utah, reached “a maximum flow rate of 107 kg/s at high temperature”, enough for “over 10 MW of electricity production” from one production well, “triple” Project Red’s

Said 10 September 2024 · Shown

Frontier More than 100 kg/s from one well in granite is about three times what Project Red circulates, and it is the result the company’s design rests on: laterals lengthened from 3,250 ft at Project Red to 5,000 ft in Cape Phase I, and to 7,500 ft in the third-generation design, with multistage stimulation adapted from shale. A national laboratory’s 2025 market report says the Cape drilling, stimulation and test results “bolstered” its projection for enhanced-geothermal cost; that is a judgement made on the company’s data, not a check of them. Lenders put US$421 million behind Phase I in March 2026 without recourse to the parent company, on data that are not public. Established A maximum is not a sustained rate, and electricity from one well is not delivery to the grid: at Project Red, net output was two-thirds of gross (1.4 of 2.1 MW). Speculative The company says its third-generation design will “produce substantially more megawatts per well”, and gives no figure. No published production record yet supports the per-well figure over years.

What is publicThe company’s announcement, and its own workshop papers on the site’s geology and stimulation, which report fracture growth tracked by microseismic monitoring. In November 2026 the chief executive said brine was reaching the first plant “at the design volume and temperature”, without figures.
What is missingFlow, temperature and pressure by well over the test; the number of producing wells behind each GeoBlock; any production history from the wells now feeding GeoBlock 1.
What would settle itProduction data from the Phase I wells over their first year, or the plant’s metered output, set against the per-well figure.

Sources: 18, 30, 4, 7, 2, 25, 22, 17

Its first unit at Cape Station, 33 MW net, entered commercial operation on 30 September 2026, the first greenfield enhanced geothermal development to reach contractual commercial operation

Said 1 October 2026 · Shown

Established The dates held. In 2023 the company targeted power from Cape by 2026; its 2024 contract with Southern California Edison set a first phase for 2026; in August 2026 it guided test power for the fourth quarter. First power came on 24 September and commercial operation on 30 September, a day inside the contractual date. Frontier That the unit is running and selling power rests on the company’s filings, which carry legal liability but are its own; nobody outside the company has published an output figure, and this page holds the claim at Shown until someone does. Frontier “Greenfield” and “contractual” do real work in the claim: in Europe an enhanced system has sold heat at Rittershoffen since 2016, and the sector’s own 2025 review puts operating commercial enhanced systems at a few megawatts electrical or a few tens of megawatts thermal, as the Institute’s Geothermal Megaprojects brief records. What is new is a 33 MW electrical unit delivering under a utility-scale contract.

What is publicThe company’s declaration, which says revenue is now being generated under its power-purchase agreement; grid export from 24 September, reported in the trade press; and the chief executive’s statement that the unit reached “that 33 megawatt net number right out of the gate”. Third-quarter revenue, US$116 thousand, is close to the second quarter’s US$113 thousand, earned before the unit ran, so it does not show the unit’s sales.
What is missingMetered net output, capacity factor, flow and temperature. The announcements do not say which buyer takes the unit’s output; the phase is contracted mainly to Southern California Edison.
What would settle itA full quarter of revenue and output, which the company says the fourth quarter of 2026 will be, and plant-level generation in a government series.

Sources: 3, 19, 20, 1, 4, 5, 16, 21, 22

Drilling costs across its first four horizontal wells at Cape fell “from $9.4 million to $4.8 million per well”, and drilling performance “fits an expected learning rate of 35%”

Said 12 February 2024 · Shown

Established The direction is not in doubt. The company’s figures are consistent across releases, papers and years, and in 2025 the national laboratory lowered its own baseline cost curves for horizontal geothermal wells by 18 to 26%, naming Project Red and Cape among the examples of faster drilling in hard rock. Frontier The laboratory’s figures for this company come from the company: they are a reproduction, not an audit, and the learning-curve preprint is the company’s own. Frontier The release’s 35% is a learning rate for drilling time. The four-well cost series by itself implies about 29% per doubling of wells drilled: $4.8 million is 51% of $9.4 million after two doublings, and the square root of 0.51 is 0.71. That is a steep curve either way, measured on four wells.

What is publicCompany releases, workshop papers and an unreviewed preprint. A national laboratory’s 2025 market report reproduces the company’s cost per foot, about $1,050 at Project Red against under about $450 for the first six Cape wells and below $300 for some later ones, citing the company’s papers and proprietary data, and records the learning rate revised by the company from 35% to 33%.
What is missingAn audited cost for each well, the spread between wells, and any cost for the deeper third-generation wells, for which the July 2026 release gives none.
What would settle itPer-well costs disclosed in the company’s filings, or a cost dataset assembled independently of the company.

Sources: 8, 13, 25, 26

Its third-generation well, Sawtooth 7, reached 19,448 ft measured depth with a 7,500 ft lateral at 460 °F in 21 days from spud to total depth, “Boosting Drilling Rates by 143% Since Its First Cape Station Well”

Said 8 July 2026 · Shown

Established Drilling deeper, longer and hotter in the same number of days is the strongest engineering claim in the sector, and the company’s table shows it directly. In footage per day from spud to total depth the three designs run at about 160, 690 and 926 ft. Handwave The headline compares Sawtooth 7 with the first Cape Station well, whose depth and drilling time the release does not give, and it does not say which rate rose by 143%. Neither ratio the table allows is 143%: Sawtooth 7 drilled about 5.8 times Project Red’s daily footage and 1.34 times the Phase I average. Frontier At 460 °F, about 238 °C, the wells run above the 150 to 175 °C at which commercial measurement-while-drilling tools are rated, a limit the Geothermal Megaprojects brief names as a bottleneck; the release does not say how it was managed.

What is publicThe company’s table of three well designs: 11,220 ft in 70 days at Project Red, an average of 14,483 ft in 21 days across Cape Phase I, and 19,448 ft in 21 days for Sawtooth 7. Trade press repeats it.
What is missingThe basis of the 143%, rates of penetration, the well’s cost, and how the downhole tools were kept working at 460 °F.
What would settle itSpud and completion dates in the state regulator’s well records, and a cost per well in the company’s filings.

Sources: 7, 24

“Expected total cost for GeoBlocks 1 through 3 remains approximately $7,000 per kilowatt”; GeoBlocks 4 to 11 are “positioned to achieve $5,500 per kilowatt of installed CAPEX”; “Our long-term target remains at $3,000 per kilowatt.”

Said 9 November 2026 · Claimed

Established The first cost figure from a built plant is the company’s own, and it is high: about $7,000 per kilowatt on about 99 MW is roughly $690 million. A first-of-a-kind plant is expected to cost more than its successors. Frontier $5,500 needs a 21% reduction, on units half again as large (about 50 MW against 33 MW) and on wells the company says it now drills faster: plausible, and not yet shown. At $5,500 the 396 MW costs about $2.2 billion; at Phase I’s rate, about $2.8 billion. Handwave No release, filing or call read for this page sets out how $3,000 would be reached. In the third quarter of 2026 the company booked US$116 thousand of revenue against US$256.7 million of capital spending.

What is publicThe figures themselves, in a results release and on the results call. The quarterly filing adds that the US$514.3 million moved into service with GeoBlock 1 “is not the standalone cost of GeoBlock 1”.
What is missingA final, audited cost for Phase I; a split between wells and surface plant; the number of wells per GeoBlock; any pathway from $5,500 to $3,000.
What would settle itThe cost of Phase I once GeoBlocks 2 and 3 are in service, and the cost of GeoBlocks 4 to 11 at completion, scheduled for the end of 2028.

Sources: 1, 2, 4

About 2 GW of capacity potential at Cape Station rests on federal approvals that have already been through National Environmental Policy Act review

Said November 2026 · Verified

Established The federal record is real, and quick by the standard of large energy projects: about 20 months from exploration approval to production approval, both on environmental assessments rather than a full environmental impact statement. The approval was issued under the previous administration, and nothing read for this page suggests it has been disturbed; the company lists a suspension of its federal rights-of-way only as a risk. Established The approval caps the federal case at about 2 GW. The company’s new figure of 8.4 GW of potential, from a consultant’s study it commissioned, is four times that, and on the company’s own account more surface disturbance than is approved could need supplemental review; contracted firm transmission out of the site is 505 MW. Frontier In Nevada the company injects under temporary 30-day permits for each well, re-issued monthly. It also tells investors that “Researchers and regulators have identified a potential link between hydraulic-stimulation activities and seismic events”. At FORGE, the federal field laboratory next to Cape, the largest induced event recorded was magnitude 1.9; the company says it tracks its own fracture growth with microseismic monitoring.

What is publicThe Bureau of Land Management’s own releases: a decision record and finding of no significant impact on an environmental assessment for exploration with up to 29 wells (13 February 2023), and approval of the Cape geothermal power project for up to 2 GW on about 631 acres, 148 of them public land (17 October 2024). Trade press adds that the decision was issued on 8 October 2024, on a finding of no significant impact from an environmental assessment, for an estimated 320 wells. The company’s own count, in its quarterly filing, is “all 80 governmental permits and approvals necessary to commence commercial operations” for Phase I and 96 of 179 for the next phase.
What is missingWhich of the 83 outstanding approvals for the next phase are federal, state or local, and when each is due; in Nevada, the underground-injection permit the company has applied for and not obtained.
What would settle itThe remaining 83 approvals granted or refused; a Nevada injection permit; any federal review of capacity beyond 2 GW.

Sources: 2, 27, 28, 29, 1, 10, 25, 30

Where it fits

The briefs this company’s work bears on, and how. Each of those briefs links back here.

Geothermal Megaprojects

Most of the brief’s contracted-against-delivered measure is this company’s disclosure, and taken claim by claim the evidence lands where the brief does. It touches four of the brief’s named bottlenecks. Durability: Project Red’s 614 days and 1.4 °C of decline are still the longest public record, and Cape has published no production data. Cost variance: the drilling figures are real and steep, but the national laboratory’s 2025 market report attributes its figures for this company to the company’s own papers and proprietary data and records the learning rate revised from 35% to 33%, so a laboratory figure is not by itself an independent check. Tool survival: the third-generation wells run at 460 °F with no published account of the tooling. Seismic siting: the company names the risk to its investors, and its federal approval covers about 2 GW of a site it now says could hold 8.4 GW. The test to carry forward is GeoBlocks 4 to 11 at $5,500 per kilowatt by the end of 2028.

AI Electricity Demand

The brief says none of the firm low-carbon options supplies a gigawatt to a data centre as of November 2026, and this company does not change that. It holds 396 MW for Google from Cape, scheduled from mid-2028 and described as the foundation for a potential Google data centre in Utah that is itself subject to engineering, state and local approvals, with an option on about 600 MW more tied to June 2030; and, separately, an agreement of 2024 to supply 115 MW to Google’s Nevada data centres through NV Energy, which a national laboratory reports as due by 2030 and whose binding status the sources read do not state. Two of the brief’s bottlenecks are in view. On tariffs meant to protect other customers, the Nevada arrangement runs through the clean transition tariff, which is designed to put the premium on the buyer rather than on other ratepayers. On wires, Cape’s output depends on 505 MW of contracted firm transmission, 105 MW of it from 2028 subject to approval, and the company cites a Utah framework, SB132, under which it could serve a data centre directly. The price is undisclosed; if the whole rise in the company’s revenue backlog in the third quarter, from US$7.2 billion to US$11.9 billion, is that contract, it implies about $90 per MWh at full output.

The numbers

Figures marked as Institute arithmetic are the Institute’s own derivations from the cited sources; the working is shown so that anyone can redo it.

QuantityValueHow it is worked outSources
Contracted against operating 1,054 MW under binding agreements; one 33 MW unit in commercial operation, beside a 3.5 MW demonstration that averaged 1.4 MW net Company figures at 30 September 2026 and April 2026. The two plants are about 3.5% of the contracted capacity by nameplate. Institute arithmetic. 1, 17
Project Red against its announcement 2.1 MW gross (60% of 3.5 MW) and 1.4 MW net (40%), averaged over 614 days The company’s April 2026 operating summary against its July 2023 figure; the percentages are Institute arithmetic. 14, 17
Project Red circulation About 36 kg/s against 63 L/s tested, which is about 56 kg/s at 175 °C: roughly two-thirds Water at about 0.89 kg per litre at 175 °C. Institute arithmetic. 15, 17
Footage drilled per day, spud to total depth About 160 ft at Project Red, 690 ft on the Cape Phase I average, 926 ft for Sawtooth 7 Measured depth divided by days, from the company’s July 2026 table. Institute arithmetic. 7
Cost per foot drilled About $1,050 at Project Red; under about $450 for the first six Cape wells; below $300 for some later ones The company’s papers and proprietary data, as reproduced in a national laboratory’s 2025 market report. 25
Phase I capital cost About $690 million for about 99 MW at the expected $7,000 per kilowatt. US$514.3 million moved into service with GeoBlock 1, which the company says is not that unit’s standalone cost. 3 × 33 MW × $7,000 per kilowatt. Institute arithmetic on the company’s figure. 1
GeoBlocks 4 to 11 at target and at Phase I’s rate About $2.2 billion at $5,500 per kilowatt; about $2.8 billion at $7,000 396 MW at each rate. Institute arithmetic. 1, 4
Implied price of the Google contract About $90 per MWh at full output, about $95 at 95%, if the whole rise in contracted revenue from 658 to 1,054 MW is that contract $11.9 billion less $7.2 billion is $4.7 billion, over 396 MW for 15 years, 52 TWh at full output. 658 MW is 1,054 less the 396 MW Google contract. Institute arithmetic; the price is not disclosed. 1, 2
Revenue against capital spending, third quarter of 2026 US$116 thousand against US$256.7 million The company’s results. GeoBlock 1 entered service on the quarter’s last day. The second quarter, before the unit ran, had US$113 thousand. 1, 5
Cape’s stated scale 8.4 GW of potential in a consultant’s study commissioned by the company; about 2 GW with federal environmental approval; 505 MW of contracted firm transmission; 466 MW under construction Company filings and releases of November 2026, and the land agency’s October 2024 decision. 1, 2, 10, 28

What would change this assessment

Status as of 22 November 2026. Events that are also on the Watchlist link to it.

MilestoneWhy it mattersStatusLatest
GeoBlocks 2 and 3 in commercial operation, completing Phase I at about 100 MW Completes the first plant and lets the expected $7,000 per kilowatt become a final cost. In progress As of 9 November 2026 GeoBlock 2 was synchronised and delivering test energy and GeoBlock 3 was in cold commissioning; both are scheduled for commercial operation by 1 January 2027. [1]
Net output, flow and temperature from GeoBlock 1, or a full quarter’s revenue and output from it The first measure of whether the Cape wells deliver what the 2024 test and the plant design assume; would move the operating claims past Shown if anyone outside the company reports it. Not seen As of 9 November 2026 the company gave 33 MW net and “design volume and temperature” without figures, and said the fourth quarter would be the first full quarter of Cape revenue. [1, 4]
A published decline rate for Project Red, and its operating status The longest public record of an engineered reservoir of this kind; every thirty-year model assumes durability. In progress In April 2026 the company reported about 1.4 °C of decline after more than 500 days at constant temperature; on 9 November 2026 its chief executive confirmed a decline and said logging trials and intervention work continue there. [17, 4]
First power from GeoBlocks 4 to 11, the 396 MW contracted to Google Tests whether the drilling gains carry to 50 MW units at $5,500 per kilowatt. In progress Scheduled for mid-2028. As of 9 November 2026 drilling was about 18% complete, the first 50 MW turbines had passed factory acceptance and over 60% of the air-cooled condensers were on site. [1]
GeoBlocks 4 to 11 at full capacity, and their cost at completion Settles the $5,500 claim either way. In progress Scheduled for the end of 2028. At 30 September 2026 the phase held 96 of 179 approvals; a further 105 MW of firm transmission is due from 2028, subject to regulatory approval. [1, 2, 10]
The 83 outstanding approvals for the next phase, and a Nevada injection permit The permitting record is the claim on this page an outside body has checked; these are the parts not yet granted. In progress At 30 September 2026: 96 of 179 approvals held; the Nevada permit applied for and not obtained, with injection under temporary 30-day permits. [2]
Per-well drilling costs from audited filings or an independent dataset, including the third-generation wells Would move the cost and learning-curve claims past the company’s own figures. Not seen As of 22 November 2026 the national laboratory’s 2025 market report reproduces the company’s figures, and the July 2026 release gives no cost for Sawtooth 7. [25, 7]
Google’s option on about 600 MW more from Cape, for nearly 1 GW, and the Utah data centre it would serve Would put close to a gigawatt of enhanced geothermal behind one prospective data centre; the data centre is subject to engineering, state and local approvals. Not seen Offered with the agreement announced on 1 September 2026 and tied to June 2030; the release does not say whether that date is for exercise or delivery. [6, 23]

Sources

Statements by the company and its own papers are labelled as such; nothing the company has published has been peer reviewed.

  1. Fervo Energy, Fervo Energy reports third quarter 2026 results, Form 8-K exhibit 99.1, 9 November 2026 — Company statement. www.sec.gov/Archives/edgar/data/0001853868/000162828026071911/exhibit991earningsrelease1.htm
  2. Fervo Energy, Form 10-Q for the quarter ended 30 September 2026 — Company statement. www.sec.gov/Archives/edgar/data/0001853868/000162828026072482/frvo-20260930.htm
  3. Fervo Energy, Fervo Energy declares commercial operation at Cape Station, Form 8-K exhibit 99.1, 1 October 2026 — Company statement. www.sec.gov/Archives/edgar/data/0001853868/000162828026064103/exhibit991pressrelease10126.htm
  4. Fervo Energy, third-quarter 2026 earnings call, 9 November 2026, transcript carried by Webull — Company statement. www.webull.com/news/15894737133826048
  5. Fervo Energy, Fervo Energy reports second quarter 2026 results, 12 August 2026 — Company statement. fervoenergy.gcs-web.com/news-releases/news-release-details/fervo-energy-reports-second-quarter-2026-results
  6. Fervo Energy, Fervo Energy and Google sign 396 MW PPA, 1 September 2026 — Company statement. fervoenergy.gcs-web.com/news-releases/news-release-details/fervo-energy-and-google-sign-396-mw-ppa
  7. Fervo Energy, Learning curve continues on 3rd generation well design, boosting drilling rates by 143% since its first Cape Station well, 8 July 2026 — Company statement. fervoenergy.gcs-web.com/news-releases/news-release-details/fervo-energy-learning-curve-continues-3rd-generation-well-design
  8. Fervo Energy, Fervo Energy drilling results show rapid advancement of geothermal performance, Business Wire, 12 February 2024 — Company statement. www.businesswire.com/news/home/20240212763499/en
  9. Fervo Energy, Management team — Company statement. fervoenergy.gcs-web.com/corporate-governance/management-team
  10. Fervo Energy, Fervo Energy and Longroad Energy execute 105 megawatt long-term transmission service agreement, 18 November 2026 — Company statement. fervoenergy.gcs-web.com/news-releases/news-release-details/fervo-energy-and-longroad-energy-execute-105-megawatt-long-term
  11. Fervo Energy, Fervo Energy secures two U.S. Department of Energy awards to develop next-generation geothermal in Idaho and Nevada, 22 September 2026 — Company statement. fervoenergy.gcs-web.com/news-releases/news-release-details/fervo-energy-secures-two-us-department-energy-awards-develop
  12. Norbeck and Latimer, Commercial-scale demonstration of a first-of-a-kind enhanced geothermal system, EarthArXiv preprint (2023) — Company preprint. eartharxiv.org/repository/view/5704
  13. Norbeck, Gradl and Latimer, Deployment of enhanced geothermal system technology leads to rapid cost reductions and performance improvements, EarthArXiv preprint (2024) — Company preprint. eartharxiv.org/repository/view/7665
  14. ThinkGeoEnergy, Fervo Energy reports breakthrough in field-scale EGS project in Nevada, 18 July 2023 — Press report. www.thinkgeoenergy.com/fervo-energy-reports-breakthrough-in-field-scale-egs-project-in-nevada
  15. S&P Global Commodity Insights, US geothermal energy company pilot shows 24/7 carbon-free power production possible, 18 July 2023 — Press report. www.spglobal.com/commodityinsights/en/market-insights/latest-news/electric-power/071823-us-geothermal-energy-company-pilot-shows-247-carbon-free-power-production-possible
  16. ThinkGeoEnergy, Fervo and Google geothermal power facility starts grid supply, 29 November 2023 — Press report. www.thinkgeoenergy.com/fervo-and-google-geothermal-power-facility-starts-grid-supply
  17. ThinkGeoEnergy, Fervo highlights stable operations of Project Red geothermal project after 600 days, 14 April 2026 — Press report. www.thinkgeoenergy.com/fervo-highlights-stable-operations-of-project-red-geothermal-project-after-600-days
  18. ThinkGeoEnergy, Fervo announces technical and commercial breakthroughs at Cape Station geothermal site, 10 September 2024 — Press report. www.thinkgeoenergy.com/fervo-announces-technical-and-commercial-breakthroughs-at-cape-station-geothermal-site
  19. ThinkGeoEnergy, Fervo Energy reports first power generation at Cape Station enhanced geothermal site, Utah, 24 September 2026 — Press report. www.thinkgeoenergy.com/fervo-energy-reports-first-power-generation-at-cape-station-enhanced-geothermal-site-utah
  20. ThinkGeoEnergy, Fervo Energy announces commercial operation of first geothermal power plant in Cape Station, Utah, 1 October 2026 — Press report. www.thinkgeoenergy.com/fervo-energy-announces-commercial-operation-of-first-geothermal-power-plant-in-cape-station-utah
  21. ThinkGeoEnergy, Fervo signs 320-MW geothermal PPA with California utility, 25 June 2024 — Press report. www.thinkgeoenergy.com/fervo-signs-320-mw-geothermal-ppa-with-california-utility
  22. ThinkGeoEnergy, Fervo secures $421 million financing to support Cape Station geothermal development, 19 March 2026 — Press report. www.thinkgeoenergy.com/fervo-secures-421-million-financing-to-support-cape-station-geothermal-development
  23. ThinkGeoEnergy, Fervo Energy signs 396-MW geothermal PPA with Google for Utah data center, 1 September 2026 — Press report. www.thinkgeoenergy.com/fervo-energy-signs-396-mw-geothermal-ppa-with-google-for-utah-data-center
  24. ThinkGeoEnergy, Fervo Energy sets new drilling record with 5,900 m geothermal well at Cape Station, Utah, 23 July 2026 — Press report. www.thinkgeoenergy.com/fervo-energy-sets-new-drilling-record-with-5900m-geothermal-well-at-cape-station-utah
  25. National Laboratory of the Rockies and Geothermal Rising, 2025 U.S. Geothermal Market Report, for the US Department of Energy, OSTI 3014949 — Government. www.osti.gov/servlets/purl/3014949
  26. ThinkGeoEnergy, New study presents updated geothermal drilling cost curves, on Akindipe and Witter (NREL), 27 March 2025 — Press report. www.thinkgeoenergy.com/new-study-presents-updated-geothermal-drilling-cost-curves
  27. US Bureau of Land Management, BLM announces decision for Fervo Energy, Cape Modern Geothermal Exploration Project, 13 February 2023 — Government. www.blm.gov/press-release/blm-announces-decision-fervo-energy-cape-modern-geothermal-exploration-project
  28. US Bureau of Land Management, Biden-Harris Administration takes major steps to accelerate clean energy geothermal development on public lands, 17 October 2024 — Government. www.blm.gov/press-release/biden-harris-administration-takes-major-steps-accelerate-clean-energy-geothermal
  29. Utility Dive, on the Interior Department’s approval of the 2 GW Fervo Cape project and a proposed geothermal categorical exclusion, 21 October 2024 — Press report. www.utilitydive.com/news/interior-geothermal-fervo-energy-categorical-exclusion-nepa/730413
  30. Fercho, Norbeck and colleagues, Update on the geology, temperature, fracturing, and resource potential at the Cape geothermal project, Stanford Geothermal Workshop (2025), proceedings record — Company preprint. pangea.stanford.edu/ERE/db/IGAstandard/record_detail.php?id=38009
About this page. The Institute has no financial or other relationship with Fervo Energy and accepts no payment for including any company. This page assesses public claims; it is not investment advice. A company that believes a claim is misplaced on the ladder can send evidence through the contact page; corrections are made here and recorded on Updates. The page is reviewed by 22 February 2027, or sooner if a milestone above is met. All Frontier Companies.