Hydrostor is a real developer with real approvals. Its Willow Rock project in Kern County, California, 500 MW for eight hours, holds a California Energy Commission licence adopted on 19 December 2025, a federal environmental finding of June 2026 that clears one step towards a conditional loan guarantee of up to US$1.76 billion, and contracts for about three-fifths of its capacity. What it lacks is money and a measured plant. Construction was to start in 2023, then in 2025; the company now says financial close and groundbreaking will come “later this year”, and by 22 November neither had been announced. Its commercially contracted demonstrator, 1.75 MW at Goderich, Ontario, one of two demonstration systems the company said in 2022 had been “Operating for Years”, opened in 2019 and has published no figure for energy delivered or efficiency, so the 60 to 65% round-trip efficiency the company cites is a specification: consistent with measured Chinese plants, unchecked for its own. The business case rests on duration. No capital cost for the plant is public; its federal loan principal alone comes to about $375 per kilowatt-hour, in a band where lithium-ion keeps getting cheaper and where most long-duration offers have so far been lithium.
The company
| Founded | 2010 [8] |
| Headquarters | Toronto, Canada [1, 8] |
| Set up to make | Advanced compressed-air energy storage: plants that store air under pressure in an underground cavern and keep the heat of compression to reuse when the air is released. The company develops and operates them. [1, 10, 18] |
| Leadership | Curtis VanWalleghem, chief executive and co-founder; Jon Norman, president; Chris Phebus, chief technology officer; Beth Summers, chief financial officer [8] |
| Disclosed funding | US$250 million from Goldman Sachs in 2022; US$200 million in convertible notes and a development loan from Canada Growth Fund, Goldman Sachs Alternatives and CPP Investments in February 2025; US$230 million of equity announced on 12 August 2026 from investors including Baker Hughes and Hatch, a total that includes a convertible note committed earlier by Canada Growth Fund. The rounds overlap and are not added here. Willow Rock also holds a conditional federal commitment for a loan guarantee of up to US$1.76 billion, not finalised. [12, 1, 14] |
| Customers | Willow Rock offtake contracts with Central Coast Community Energy (200 MW for 25 years, signed 2022 and amended three times), California Community Power for member agencies including CleanPowerSF (20 years, approved January 2026) and Clean Energy Alliance (60 MW, August 2026). The Goderich plant was built under a contract with Ontario’s system operator. [11, 19, 25, 2, 10] |
| Stated plans | Financial close and groundbreaking at Willow Rock “later this year”; financial close at Silver City, Broken Hill, Australia, in the first half of 2027; a 7 GW pipeline that includes a 500 MW project in Ontario and an early-stage British project aimed at the second window of Ofgem’s long-duration cap-and-floor scheme [1, 22, 7] |
What it claims, and how far each claim has got
Each claim is placed on the Institute’s evidence ladder, which measures how far the public evidence for a claim has got, not whether the claim is true: Claimed, Described, Shown, Verified, Repeated and In use. The definitions are on the Frontier Companies page. Flags inside each assessment follow the rest of the site: Established, Frontier, Speculative and Handwave.
The US$230 million round progresses Willow Rock “to financial close later this year”, and the company “plans to break ground later this year”
Established The record is of dates that moved. In 2022 the company showed construction starting in the third quarter of 2023 and operation in 2026–27. In January and February 2025 construction was targeted for later that year. Its first buyer, Central Coast Community Energy, amended the contract in December 2023 to give “more time for [Hydrostor] to secure financing”, again in December 2024, when the financing and construction-start deadlines moved to 23 November 2025, and a third time after an April 2025 request in which the company cited permitting, interconnection, inflation and financing costs, and had still not secured financing. Frontier The company’s strongest case is that the obstacles it named have since been cleared or reduced: the state licence came in December 2025 and the federal environmental review in June 2026; Baker Hughes, an equipment maker, and Hatch, the engineering firm leading design and execution, took equity; and two more buyers signed in 2026. The case against is that none of this is money lent, and that the federal guarantee, conditional since January 2025 and reported as uncertain a month later after a federal order paused disbursements, is the evident source of most of the debt. With under six weeks of the year left, no close had been announced.
| What is public | The statement. The permits are in hand, a federal environmental finding was signed on 30 June 2026, and offtake contracts cover about 310 of the 500 MW. No lender, debt amount or closed federal guarantee has been named. |
| What is missing | A closed financing with its lenders and amounts, and a final decision by the Department of Energy on the guarantee. |
| What would settle it | An announced financial close naming its lenders by 31 December 2026 settles it for; a new date, or a fourth amendment to the first offtake contract, settles it against. |
“On-site work has officially begun on the Willow Rock Energy Storage Center as of July 2026”
Frontier Six days after saying work had begun, the company said it “plans to break ground later this year”. The two statements agree only if the July work is preparatory, short of the construction a lender would finance, and the company has not said which it is. Established The federal environmental assessment gives the sequence: about 60 months of construction from July 2026, with commercial operation in month 61. On that table a plant genuinely under construction from July 2026 operates in mid-2031, although the assessment’s text says operation is anticipated by 2030. The date is Institute arithmetic on the assessment’s own schedule.
| What is public | The company’s statements, repeated in trade press: work “already started” (12 November 2026); the project “advances through construction” (26 October 2026). The federal environmental assessment scheduled construction to begin in July 2026. |
| What is missing | What the work is, whether it includes the shafts or the cavern, and whether it meets the construction-start milestone in the offtake contracts. |
| What would settle it | A dated start of shaft sinking or cavern excavation, or a construction notice in the state licence’s compliance record. |
Willow Rock obtains final approval for its power plant licence from the California Energy Commission
Established A regulator’s decision is the strongest outside check a developer can get before it builds, and the primary record fixes the date: the Commission heard and approved the project on Friday 19 December 2025. It adopted a statement of overriding considerations for visual resources, which means it found the visual impact significant after mitigation and approved the project anyway. Established The review was paused while the company reassessed the suitability of its cavern and transmission, which its first buyer called the “driver” of the first contract delay. The licence is what makes the plant buildable. It is not evidence that the plant works.
| What is public | The Commission’s Notice of Determination under docket 21-AFC-02, recording approval on 19 December 2025 with a statement of overriding considerations for visual resources; the Commission’s hearing notice for the same day; and a San Francisco resolution of April 2026 that relies on the same final decision. |
| What is missing | Nothing for the licence itself. A licence tests siting, safety and environmental effects, not how much energy the plant returns. |
| What would settle it | Settled. Any later change to the licence would appear in the same docket. |
A 500 MW / 4,000 MWh plant giving eight hours of continuous discharge, with a 50-year operating life
Established The duration is the point. The largest operating compressed-air plants, in China, are four- and five-hour assets; Willow Rock is designed for eight, the band in which the Energy Storage Revolutions brief places the contested crossover with lithium-ion. The company’s strongest technical argument, made by its chief technology officer in November 2026, is that every part of the plant, from compressors and turbines to heat management and the cavern, is field-proven equipment from the oil, gas and power industries. Frontier What is new is the combination at this size, about 286 times Goderich’s output. No regulator has tested performance: the licence and the environmental review accept the design’s effects, not its output.
| What is public | The licensed design and the federal environmental assessment: 520 MW and 4,160 MWh gross, 500 MW and 4,000 MWh net; one cavern 2,000 to 2,500 feet down; about 1,400 acre-feet of water for construction and the first filling of its reservoir, and no more than 4 acre-feet a year in operation. |
| What is missing | Any measurement from a plant of this design larger than 1.75 MW. |
| What would settle it | Commissioning and acceptance tests at Willow Rock, reported by its buyers or the grid operator. |
The system can achieve “around 60% to 65% round-trip efficiency”, in the words of its president; in 2022, “60%+” from the grid back to the grid
Frontier The figure is plausible: the brief records measured efficiencies of 64% and 70.4% at two Chinese compressed-air plants. It is also low against lithium-ion’s 85 to 95%, and the difference is energy that must be bought. To deliver 4,000 MWh at 60 to 65%, Willow Rock must draw 6,150 to 6,670 MWh; a lithium-ion plant at 90% would draw about 4,440. Handwave The 2022 figure is defined at the grid connection under daily full-power cycling, which is the right boundary; the 2026 figure, relayed by the trade press, comes with none. Seven years after Goderich came online, no measured figure from it has been published, and that absence is the finding.
| What is public | The statements. No measured efficiency has been published for Goderich, the company’s commercially contracted plant, or for its other demonstration system. |
| What is missing | A measured round-trip efficiency, with its boundary and duty cycle, from any Hydrostor plant. |
| What would settle it | A year of metered charge and discharge at Goderich, or acceptance tests at Willow Rock. |
Goderich: 1.75 MW of output and more than 10 MWh in a former salt cavern in Ontario, opened on 22 November 2019 under a contract with Ontario’s system operator; the company’s projects page now calls it “The World’s First Commercially Contracted A-CAES Facility”
Established The plant was built, connected and contracted. It is a real run, and in that sense the technology has worked at small scale. It was developed with NRStor, with Hydrostor supplying the technology, and it is small: 1.75 MW out against 2.2 MW in. Frontier Nothing it has done is public in a form anyone could check, yet the company’s 2022 slides set it under “Proven technology”. This is the gap the brief calls the largest evidentiary hole in the subject, and it matters most here because Goderich is the largest operating evidence the company has cited behind a 500 MW plant.
| What is public | Trade reporting of the opening, with the ratings and a contract with Ontario’s system operator; the company’s 2022 statement that its demonstration systems had been “Operating for Years”. |
| What is missing | Megawatt-hours delivered, cycles, availability and measured efficiency for any year, and the plant’s operating status in 2026. |
| What would settle it | An operating record published by the company or by Ontario’s system operator. |
Silver City, a 200 MW / 1,600 MWh plant at Broken Hill, New South Wales, is “currently aiming to reach financial close in the first half of next year”
Established The approvals are real and the purpose is specific. Broken Hill sits at the end of a single 260 km line, and Silver City was chosen to replace two ageing 25 MW diesel generators, with 50 MW / 250 MWh held back for outages. A local business’s court challenge to the approval was settled by conciliation. Established The dates have moved as Willow Rock’s did. At planning approval in February 2025 the state said work was expected to start that year and take three to four years. In December 2025 the company’s industry-participation plan said financial close was “imminent and achieved”, a phrase that contradicts itself, and gave completion as 30 December 2030. In September 2026 close was set for the first half of 2027.
| What is public | State planning approval in February 2025; grid-connection approval from the market operator and the transmission company, announced by the company on 1 September 2026; selection by Transgrid in 2020 to back up the town’s supply; an industry-participation plan approved by the federal authority in December 2025. |
| What is missing | Financing, a construction contract and a start date. |
| What would settle it | An announced financial close by 30 June 2027 settles it for; another new date settles it against. |
The chief technology officer wrote in November 2026 that “an A-CAES facility is a massive $2 billion project”, without naming Willow Rock
Frontier No capital cost for Willow Rock is public. The nearest public figure is its debt: the federal commitment’s US$1.5 billion of principal alone is about $375 per kilowatt-hour of rated energy, and the cost of a project exceeds its loan. That is already above both survey figures for compressed air in the brief, $293 and $201, well above the roughly $217 the brief calculates for the 600 MW Huai’an plant, and about 19 times the $20 per kilowatt-hour at which peer-reviewed modelling finds long-duration storage cuts system costs by a tenth. Read as Willow Rock’s cost in US dollars, the chief technology officer’s general $2 billion would be about $500. Speculative On the company’s argument the figure that matters is the cost of each added hour, low for a cavern and high for a rack of cells. No such figure is public for Willow Rock, so neither side of that argument can yet be checked against it.
| What is public | The statement, about A-CAES facilities in general, with no breakdown, currency or project named. The federal conditional commitment of January 2025 for Willow Rock was for about US$1.5 billion of principal and about US$280 million of capitalised interest. |
| What is missing | A capital cost split into power and energy components, whether the figure includes financing costs, and the contract price per unit delivered. |
| What would settle it | Disclosure at financial close, or in filings by the public buyers. |
Where it fits
The briefs this company’s work bears on, and how. Each of those briefs links back here.
Energy Storage Revolutions
The brief uses Willow Rock as its evidence that permitting, interconnection and financing bind before technology does, its sixth bottleneck, and the record supports that reading: the licence and the federal environmental finding are in hand, and the binding test is now financial close, which the company has promised for 2026. If it closes and is built, Willow Rock would be by far the largest adiabatic compressed-air plant in the West, where the brief’s only operating example is Goderich at 1.75 MW; it would discharge for eight hours, the duration at which the brief locates the contested crossover with lithium-ion, twice the four hours of the largest Chinese compressed-air plant. It also bears on the brief’s fourth frontier question, whether anything built actually delivers: the brief names Goderich among the plants with no published delivered-energy data, and the company has still published none. On cost, no figure for the plant is public, but its federal loan principal alone is about $375 per kilowatt-hour, nearly nineteen times the brief’s $20 threshold, and sellers have so far offered lithium: of 30 long-duration offers to one California buyer group, Willow Rock was the only one not using lithium-ion, and the group approved it.
The numbers
Figures marked as Institute arithmetic are the Institute’s own derivations from the cited sources; the working is shown so that anyone can redo it.
| Quantity | Value | How it is worked out | Sources |
|---|---|---|---|
| Willow Rock’s rating | 500 MW / 4,000 MWh net, eight hours; 520 MW / 4,160 MWh gross | The licensed design, as described in the federal environmental assessment. | 3, 18 |
| Goderich, the commercially contracted demonstrator | 1.75 MW out, 2.2 MW in, more than 10 MWh. Willow Rock is about 286 times its output and up to about 400 times its energy | Ratings reported at the opening, November 2019; 500 ÷ 1.75 and 4,000 ÷ 10. Institute arithmetic. | 10 |
| Federal loan principal per kilowatt-hour | About $375 on the net rating: a floor, not a cost | US$1.5 billion of principal over 4,000 MWh. Institute arithmetic. | 14 |
| Federal conditional commitment | Up to US$1.76 billion: about US$1.5 billion of principal and about US$280 million of capitalised interest | As reported at the January 2025 announcement. Not finalised: the environmental finding of 30 June 2026 says it is not a decision on the guarantee. | 14, 18 |
| The first offtake contract | 200 MW / 1,600 MWh for 25 years, capped at US$775 million and raised to US$895 million (15.5%) in the third amendment: about $14.90 per kilowatt-month at the new cap | US$895 million over 200,000 kW and 300 months. Institute arithmetic on the buyer’s board figures as reported. | 11 |
| Capacity under contract | About 310 of 500 MW, or 62% | 200 MW to Central Coast Community Energy, a reported 50 MW to California Community Power and 60 MW to Clean Energy Alliance. Institute arithmetic. | 11, 15, 2 |
| Charging energy for one full discharge | 6,150 to 6,670 MWh at the company’s 60 to 65%; about 4,440 MWh for lithium-ion at 90% | 4,000 MWh divided by each efficiency. Institute arithmetic on a claimed figure. | 15 |
| Stated construction starts | Third quarter of 2023 (stated in 2022); 2025 (stated in January and February 2025); “later this year” (stated in August 2026) | The company’s 2022 presentation, reporting of the January 2025 loan commitment and the February 2025 financing, and the August 2026 release. | 9, 14, 12, 1 |
| Stated commercial operation | 2026–27 (2022 presentation); June 2028 in the first contract, extended 18 months in December 2023 with a further 13 months requested in April 2025; 2030 (January 2025); 1 July 2030 (California Community Power, April 2026); month 61 of a build from July 2026, about July 2031 (federal assessment, June 2026) | Each as stated by its source; the July 2031 date is Institute arithmetic on the assessment’s schedule. | 9, 11, 14, 19, 18 |
| Silver City | 200 MW / 1,600 MWh for A$638 million, about A$399 per kilowatt-hour; completion stated as 30 December 2030 | The state’s February 2025 figure and the December 2025 industry-participation plan; 638 ÷ 1.6. Institute arithmetic. | 20, 24, 21 |
What would change this assessment
Status as of 22 November 2026. Events that are also on the Watchlist link to it.
| Milestone | Why it matters | Status | Latest |
|---|---|---|---|
| Financial close at Willow Rock, with its lenders named | The company’s own dated test: on 12 August 2026 it said close would come “later this year”. | Not seen | Not announced as of 22 November 2026. [1] |
| Groundbreaking, and the start of shaft and cavern construction | Separates the preparatory work the company says began in July 2026 from construction on the federal schedule. | In progress | On 12 November 2026 the company said it had “already started work”; no groundbreaking had been announced. [2, 5] |
| A final decision on the federal loan guarantee of up to US$1.76 billion | The evident source of most of the debt; conditional since January 2025. | In progress | Environmental finding signed on 30 June 2026, stated not to be a decision on the guarantee. [14, 18] |
| A fourth amendment to the Central Coast Community Energy contract, or new dates in the other buyers’ contracts | The public buyers’ board papers are where the slips have appeared first. | Not seen | Three amendments by November 2025; California Community Power expected operation on 1 July 2030 as of April 2026. [11, 19] |
| An operating record for Goderich: energy delivered, cycles, availability and measured round-trip efficiency | Would move the efficiency claim off “claimed” and the plant past “shown”. | Not seen | Nothing published as of 22 November 2026. [10] |
| Financial close at Silver City, Broken Hill | The second project’s dated test, after a close described as “imminent and achieved” in December 2025. | Not seen | Aimed for the first half of 2027, as of 2 September 2026. [21, 22] |
| Commercial operation and acceptance tests at Willow Rock | The first measurement of the design at scale, and the test of the eight-hour claim. | Not seen | Expected on 1 July 2030 by one buyer as of April 2026; the federal construction schedule implies mid-2031. [19, 18] |
Sources
Statements by the company and its own papers are labelled as such; nothing the company has published has been peer reviewed.
- Hydrostor, Hydrostor secures $230 million to progress advanced compressed air energy storage projects, 12 August 2026 — Company statement. hydrostor.ca/hydrostor-secures-230-million-to-progress-advanced-compressed-air-energy-storage-projects
- Hydrostor, Willow Rock Energy Storage Center signs offtake agreement with Southern California community choice aggregator, Business Wire, 6 August 2026 — Company statement. www.businesswire.com/news/home/20260806689565/en
- Hydrostor, Willow Rock Energy Storage Center obtains final approval for power plant license, Business Wire, 19 December 2025 — Company statement. www.businesswire.com/news/home/20251219659175/en
- Hydrostor, Hydrostor reaches key milestone with grid connection approval for Silver City Energy Storage Centre, 1 September 2026 — Company statement. hydrostor.ca/hydrostor-reaches-key-milestone-with-grid-connection-approval-for-silver-city-energy-storage-centre
- Chris Phebus, From proven components to bankable projects, Hydrostor, 12 November 2026 — Company statement. hydrostor.ca/from-proven-components-to-bankable-projects
- Hydrostor, Building more than energy infrastructure in Kern County, 26 October 2026 — Company statement. hydrostor.ca/building-more-than-energy-infrastructure-in-kern-county
- Hydrostor, Projects — Company statement. hydrostor.ca/projects
- Hydrostor, Our company — Company statement. hydrostor.ca/our-company
- Curtis VanWalleghem, Hydrostor presentation hosted by the US National Energy Technology Laboratory (2022) — Company statement. netl.doe.gov/sites/default/files/netl-file/22TMCES_VanWalleghem.pdf
- Energy-Storage.News, Grid-connected advanced compressed air energy storage plant comes online in Ontario, 26 November 2019 — Press report. www.energy-storage.news/grid-connected-advanced-compressed-air-energy-storage-plant-comes-online-in-ontario
- Energy-Storage.News, Hydrostor and 3CE amend Willow Rock ESA for third time, ‘permitting and interconnection challenges’ to blame, 19 November 2025 — Press report. www.energy-storage.news/hydrostor-and-3ce-amend-willow-rock-esa-for-third-time-permitting-and-interconnection-challenges-to-blame
- Energy-Storage.News, Hydrostor secures US$200 million for advanced compressed air energy storage projects, 18 February 2025 — Press report. www.energy-storage.news/hydrostor-secures-us200-million-for-acaes-projects
- Energy-Storage.News, US roundup: Hydrostor A-CAES project, Hawaiian Electric on Maui, Peregrine picks Wärtsilä for 500MWh Texas BESS, 24 December 2025 — Press report. www.energy-storage.news/us-roundup-hydrostor-a-caes-project-hawaiian-electric-on-maui-peregrine-picks-wartsila-for-500mwh-texas-bess
- Renewable Energy World, DOE’s billion dollar bet: the largest-ever loan supporting long duration energy storage, 9 January 2025 — Press report. www.renewableenergyworld.com/storage/does-billion-dollar-bet-the-largest-ever-loan-supporting-long-duration-energy-storage
- ESS News, Hydrostor signs offtake agreement for CAES project in southern California, 7 August 2026 — Press report. www.ess-news.com/2026/08/07/hydrostor-signs-offtake-agreement-for-caes-project-in-southern-california
- California Energy Commission, Notice of Determination, Willow Rock Energy Storage Center, docket 21-AFC-02, 19 December 2025 — Government. nods.resources.ca.gov/wp-content/uploads/2025/12/NDEWillowRockNEW.pdf
- California Energy Commission, public hearing on the Willow Rock Energy Storage Center, 19 December 2025 — Government. www.energy.ca.gov/event/meeting/2025-12/california-energy-commission-public-hearing
- US Department of Energy, Environmental Assessment DOE/EA-2326 and Finding of No Significant Impact for the Willow Rock Energy Storage Center, signed 30 June 2026 — Government. www.energy.gov/sites/default/files/2026-07/260630_EA_WillowRock_FONSI_signed.pdf
- San Francisco Board of Supervisors, Resolution No. 201-26, CleanPowerSF participation in California Community Power’s Willow Rock long-duration storage project, 14 April 2026 — Government. media.api.sf.gov/documents/r0201-26.pdf
- NSW Government, Broken Hill’s energy future secured by hi-tech air energy storage system, 25 February 2025 — Government. www.nsw.gov.au/ministerial-releases/broken-hills-energy-future-secured-by-hi-tech-air-energy-storage-system
- Australian Industry Participation Authority, Silver City Energy Storage plan summary, approved 19 December 2025 — Company statement. www.industry.gov.au/sites/default/files/aip/2025-12/silver_city_energy_storage_plan_summary_december_2025.pdf
- RenewEconomy, Complex and innovative compressed air energy storage project cleared to support blackout-prone grid, 2 September 2026 — Press report. reneweconomy.com.au/complex-and-innovative-compressed-air-energy-storage-project-cleared-to-support-blackout-prone-grid/amp
- Hydrostor, Hatch and Hydrostor announce strategic execution partnership and equity agreement to deliver advanced compressed air energy storage — Company statement. hydrostor.ca/hatch-and-hydrostor-announce-strategic-execution-partnership-and-equity-agreement-to-deliver-advanced-compressed-air-energy-storage
- Energy-Storage.News, Hydrostor sees 1,600MWh advanced compressed air energy storage project in Australia approved, February 2025 — Press report. www.energy-storage.news/hydrostor-sees-1600mwh-compressed-air-energy-storage-project-in-australia-approved
- Redwood Coast Energy Authority, board meeting supplemental materials, including California Community Power’s Willow Rock energy storage agreement, February 2026 — Government. redwoodenergy.org/wp-content/uploads/sites/850/2026/02/260226-Board-Mtg-Supplemental-Materials.pdf